PeopleSoft Hardware Infrastructure to be Replaced

UTShare On-Premise Build and Migration Project

What is Happening?

UT Shared Information Services (UT SIS) has embarked on a project to replace the old hardware infrastructure with new state of the art equipment that is adequately scaled to support the academic institutions using the UTShare/PeopleSoft systems.   The migration to this new infrastructure affects all PeopleSoft environments being used on our campus.

The new infrastructure will use the Arlington Regional Data Center (ARDC) as the primary site, and the UT Austin Data Center will be the secondary site.  In the final design, there will be redundancy between the two sites. 

The project’s purpose is to build an infrastructure that is stable and standardized (where possible) and that provides redundancy for UT System campuses.   Campuses should see increased system performance, and unscheduled down time should rarely occur. 

What is the Impact?

The impact to the UTSA campuses will be mostly transparent.  In partnership with UT SIS, The PeopleSoft Support & Sustainment Center (PSSC) will coordinate and validate changes that affect our campus.  However, there may be impacted items within your area that you can help identify, most notably:

  • Shared.utsystem.edu Domain names that you have imbedded within webpages
  • Shared.utsystem.edu Domain names within any documentation
  • Shared.utsystem.edu Domain names marked as browser favorites or shortcuts 

The existing Shared.utsystem.edu domain name will be changed to utshare.utsystem.edu.  

UTSA Direct Campus Impact

April 8-10 - PeopleSoft/UTShare will be unavailable during the cutover period.

  • Access to PeopleSoft for employee information, and UTSA business processes will not be available during this time.

On Premise Cutover Scedule

  • Saturday, April 8, 2017 from 12:00 a.m. CT to Monday, April 10, 2017 time to be determined
    • The start time has been approved by campuses to minimize impact to payroll processing
    • The end time will be determined following the mock Production cutover
  • Tuesday, April 11, 2017 – 8:00 a.m. CT - Go Live, PeopleSoft - Production environment available to campuses
    • This time is subject to change pending outcome of UT SIS and campus testing

PSSC can assist with any remaining validation or updates if you need support.  We will also continue to provide updates as information becomes available and as the transitions occur.  As of now, the PSSC-led validation testing will be completed by April 3. The tentative go-live date is April 11, 2017.
We appreciate your patience during this time.  Please contact PSSC at (210) 458-7762 if you have any questions or concerns.

Stay Updated with PeopleSoft news and SPOC Spotlights

BAGPs

 

3-31-2017