| 1604 Campus Projects | |
| University Center Expansion, Phase III | |
|
Aerial View Paseo View |
Size: 59,078 new gross square feet 68,285 renovated square feet Total Project Cost: $33,300,000 Type of Project: New Construction Project Delivery: CM at Risk PROJECT TEAM: Architect: Perkins + Will Architects Construction Manager: SpawGlass Proposals due: 9/6/2006 Project start date: 1/15/2007 Substantial Completion: 6/1/2008 |