Status Update - 5/16/19
	    May 16, 2019
	
    | Status Item | Current Status | Previous Status | Comment | 
| Schedule | yellow | yellow | Banner Integration Delay | 
| Resources | yellow | yellow | Losing access to Huron resources can potentially impact timeline | 
| Financials | green | green | |
| Quality | green | green | |
| Project Issues | yellow | yellow | Banner/Axiom Integration data load is delayed. Several failed preliminary test scripts | 
| Key Deliverables | % | Comments | Timeline | 
| Requirement Sign-off | 100% | 12/14 | |
| Data Model/Mapping | 100% | 1/12 | |
| Build | 100% | 4/19 | |
| Integration | 67% | Still awaiting final tables to be loaded | 5/3 | 
| Training/UAT | 33% | This week: Train-the-Trainer | 5/15 | 