Banner 8.14 User Testing - complete
April, 2018
Go/No Go Decision For Banner 8.14 Upgrade - complete
April, 2018
Banner 8.14 Upgrade Weekend - complete
April, 2018
Go Live Banner 8.14 - complete
April, 2018
Ellucian Solution Manager (ESM) Implemented - complete
June 2018
Banner 9 Environment Created - complete
July 2018
Application Navigator (AppNav) Implemented - complete
October 2018
Banner 9 Upgrade Essentials Engagement DEVL PPRD - complete
October 2018
Banner Admin Pages User Testing - complete
November 2018
- Testing I (NPB 1.412) - complete
- Testing II (NPB 1.412) - complete
- Testing III (NPB 1.412) - complete
Banner Admin Pages Trained (phased process) - complete
November, 2018 - June, 2019
Banner 9 Administrative Pages PROD Implemented - complete
December 2018
- Backups taken, Banner 8 upgrades applied - complete
- Banner 9 upgrades will be applied, install and configure Application Navigator, Administrative Common, additional software tools for support and upgrades and then localizations applied - complete
- Email to Banner Core Users and testers, User testing of upgrade in Production - complete
- Banner 8 is up and ready for use, Banner 9 will be released in phases - complete
Deploy Link to Financial Aid - complete
January 2019
Deploy Link to Financial Services - complete
February 2019
Banner Forms Conversion - complete
February, 2019 - April, 2019
Banner Admin Pages User Testing - complete
June 2019
- Testing I (NPB 1.412) - complete
- Testing II (NPB 1.412) - complete
- Testing III (NPB 1.412) - complete
Banner Admin Pages Remediation (Ellucian) - complete
April, 2019 - June, 2019
Deploy Link campus-wide - complete
September, 2019
Banner 9 Admin Pages User Guidance Sessions - complete
September, 2019
- Guidance I (NPB 1.1412) - complete
September 16, 2019 1:00 PM-4:00 PM
- Guidance II (NPB 1.1412) - complete
September 18, 2019 8:00 AM-12:00 PM
- Guidance III (NPB 1.1412) - complete
September 23, 2019 1:00 PM-5:00 PM
- Guidance IV (NPB 1.1412) - complete
September 25, 2019 8:00 AM-12:00 PM
- Guidance V (MNT 1.103B.8 - Downtown) - complete
October 08, 2019 8:00 AM-12:00 PM
- Guidance VI (MNT 1.103B.8 - Downtown) - complete